MassDOT Issues RFP for Sagamore Bridge Replacement

The move unlocks a roughly $2.4 billion federal‑state‑Corps funding package that launches a competitive design‑build process aimed at starting construction in winter 2027–28.

Overview

  • Project managers released a design‑build request for proposals that formally moves the Sagamore Bridge from planning into procurement and invites final bids next year.
  • MassDOT published a public schedule calling for final proposals in May 2027, public bidding in July 2027, a notice to proceed in late 2027, and construction to begin in winter 2027–28.
  • The funding package for the Sagamore replacement totals about $2.4 billion made up of roughly $1.3 billion in federal grants, $750 million in state support, and $350 million from the U.S. Army Corps of Engineers.
  • The winning contractor will be required to sign a project labor agreement with regional building trades unions and the project will include wider travel lanes, a 12‑foot entry/exit lane, and a 14‑foot shared‑use path.
  • Earlier this year the state used eminent domain to acquire more than a dozen homes in the Round Hill neighborhood and funding and planning for the nearby Bourne Bridge replacement remain under development.