Overview
- Regulators set final briefs for Feb. 12, 2027, with public hearings in the affected counties in late September 2026 and evidentiary hearings Dec. 8–18, 2026.
- PSEG must file updated analyses and field studies by March 2, 2026, and may include refreshed reliability data from PJM in that submission.
- The PSC rejected the expedited timeline PSEG sought for a March 2026 decision tied to a June 2027 in-service date, saying it would not accept blackout claims without examining evidence and alternatives.
- State reviewers previously deemed PSEG’s application incomplete, and the PSC said the company has not fully addressed those concerns.
- Opposition from landowners continues, with ongoing federal litigation over property access and a recent denial of PSEG’s request for U.S. Marshals to accompany survey crews.