Overview
- State transportation leaders reset the cost range to $4.3–$5.2 billion and now expect traffic to return in late 2030, two years later than first projected.
- The original $1.7–$1.9 billion figure was a rapid, preliminary estimate to access federal emergency relief within weeks of the March 2024 collapse.
- Key drivers include sharply higher material costs, tougher federal standards for resilience, and a vastly expanded pier‑protection system to guard against ship strikes.
- Design work is about 70% complete, demolition of remnants is underway, and early construction testing has begun with Kiewit leading the rebuild.
- Maryland is pursuing damages from the Dali’s owner as the NTSB meets to finalize findings following preliminary evidence of electrical failures on the ship.