Particle.news
Download on the App Store

Maryland Doubles Key Bridge Rebuild Estimate to $4.3–$5.2 Billion, Delays Opening to 2030

Officials cite higher material prices under stricter federal resilience rules.

Overview

  • State transportation leaders reset the cost range to $4.3–$5.2 billion and now expect traffic to return in late 2030, two years later than first projected.
  • The original $1.7–$1.9 billion figure was a rapid, preliminary estimate to access federal emergency relief within weeks of the March 2024 collapse.
  • Key drivers include sharply higher material costs, tougher federal standards for resilience, and a vastly expanded pier‑protection system to guard against ship strikes.
  • Design work is about 70% complete, demolition of remnants is underway, and early construction testing has begun with Kiewit leading the rebuild.
  • Maryland is pursuing damages from the Dali’s owner as the NTSB meets to finalize findings following preliminary evidence of electrical failures on the ship.