Overview
- Portable classrooms now occupy the lower yard, with the upper yard reserved for construction of permanent buildings slated for completion in the 2028–29 school year.
- Enrollment has fallen to about 130 students from roughly 310 before the fire, reflecting a broad dispersion of families across other schools.
- District officials posted soil and air test results showing the campus environment is safe and will continue monitoring as nearby debris removal proceeds; on‑site mental health services are available this week.
- The interim campus cost about $19 million within a reconstruction program budgeted up to roughly $600 million, funded upfront by LAUSD’s $9 billion construction bond with reimbursement sought from disaster relief and insurance.