Maharashtra Orders Work Halt on Adani Tarali Pumped Storage Project

The move follows reports that online filings sharply reduced the project’s declared cost, a change that would cut mandatory wildlife‑conservation payments and has prompted a central probe.

Overview

  • The Maharashtra Forest Department issued a show‑cause notice to Adani, instructed an immediate stop to work at the 1,500 MW Tarali site, and asked the company to submit statutory approvals, project maps and a written explanation within three days.
  • News reports say an online affidavit lowered the declared project cost from Rs 5,675 crore to Rs 56.75 crore, a reduction that would shrink a required conservation payment to the Sahyadri Tiger Reserve from about Rs 227 crore to roughly Rs 2.27 crore.
  • The central government has opened a probe into the filings and the conservation‑payment calculation, putting national wildlife clearances and agency records under scrutiny.
  • Adani Group denied any attempt to reduce conservation obligations and said the smaller online figure covered only preliminary site investigation and survey costs while the State Board for Wildlife considered the full Rs 5,675 crore project cost; the company also says the project is on private land outside notified protected buffers.
  • This matter matters because wildlife conservation fees are set from declared project costs and a finding of improper filings could force higher payments, delay the project while NBWL and SBWL clearances are rechecked, and spur further political and parliamentary scrutiny.