Overview
- The Tasmanian government published the $1.23 billion stadium estimate on November 23–24 and said precinct infrastructure ($132 million) and project delivery costs ($183 million) raise the disclosed bill to $1.54 billion.
- Macquarie Point Development Corporation has entered final negotiations with preferred tenderer BESIX Watpac after submitting a final price in early November and aims to sign a construction contract by Christmas 2026.
- Officials have not revealed the contingency amount that covers unexpected costs, and applying the prior contingency rate used in earlier estimates would push the total toward about $1.76 billion.
- Under the funding deal the state's contribution was capped at $875 million with $240 million from the federal government and $15 million from the AFL, but rising costs and extra borrowings mean the cap is under strain.
- Cabinet is due to consider the updated budget on November 30, with the government warning global supply pressures, higher labour and materials costs and project complexity drove the $100 million increase.