Macquarie Point Stadium Construction Cost Rises to $1.23 Billion

The increase pushes the full Macquarie Point program to $1.54 billion, prompting calls for greater cost disclosure before a November 30 cabinet review.

Overview

  • The Tasmanian government disclosed Tuesday that the stadium construction estimate has risen from $1.13 billion to $1.23 billion and that precinct enabling works and delivery costs bring the program total to $1.54 billion.
  • The $1.54 billion figure includes $132 million for precinct infrastructure such as power and water upgrades and $183 million for project delivery and MPDC costs.
  • Under the funding deal the state's contribution is capped at $875 million while the federal government has pledged $240 million and the AFL $15 million, leaving any excess to be found outside the state cap.
  • The Macquarie Point Development Corporation is in final negotiations with preferred tenderer BESIX Watpac after receiving a final price in November and hopes to sign a build contract by Christmas, with cabinet to consider the updated budget on November 30.
  • Ministers say global cost pressures — including the US–Iran war, high oil and materials prices, higher labour costs and project complexity — drove the rise, and critics are demanding publication of contingency and precinct cost details and extended parliamentary scrutiny into December.