Overview
- Transport for NSW said the tunnel fully reopened in both directions ahead of the Friday morning peak following overnight repairs to damaged sprayed-concrete lining.
- Engineers identified two large bulges in the westbound roof during an overnight inspection, triggering a safety shutdown between Haberfield and North Strathfield.
- Drivers reported being stuck in the tunnel and on approaches for up to three-and-a-half to four hours before one westbound lane reopened in the afternoon.
- NSW Roads Minister Jenny Aitchison and Transport for NSW leaders criticised Transurban for weak communication and for initially declining government engineering support.