M25 in Surrey Reopens Early After Weekend Closure
National Highways reports successful progress on bridge demolition and gantry installation.
- The M25 in Surrey reopened eight hours ahead of schedule after a weekend closure for bridge demolition and gantry installation.
- National Highways South-East reported making 'good progress' during the closure, which was the first planned daytime shutdown since 1986.
- Traffic congestion was less severe than anticipated, with a significant reduction in traffic levels and manageable delays through diversion routes.
- Local residents and council officials noted the situation was better than expected, with some enjoying the quieter conditions.
- Four more daytime closures of the M25 are planned up to September as part of a project to increase lanes at junction 10.