Limited Metro Tunnel Services Set for November, Full Opening Pushed to 2026

Delays at CBD stations compounded by unproven signalling systems have forced a scaled-back launch plan alongside a protracted testing programme

Image
Image
Image

Overview

  • The Victorian Government has confirmed a November 2025 soft launch of off-peak Metro Tunnel services with a full timetable deferred to early 2026 pending final timetabling.
  • Construction at Town Hall and State Library stations remains incomplete, restricting initial operations to non-peak hours.
  • New high-capacity signalling and platform screen doors have entered trial operations but require extended testing before routine use.
  • Upon full deployment, Sunbury and Dandenong lines will be diverted from the City Loop through the tunnel’s five new stations.
  • Up to $888 million in bonus payments to the Cross Yarra Partnership for a 2025 opening remains under negotiation with questions over eligibility for a staged launch.