Lima Sets Vía Expresa Grau Trial Run in 60 Days as Work Hits 90%

The 2.8 km link will for the first time enable a direct transfer from the Metropolitano to Metro Line 1.

Overview

  • The corridor, which Mayor Renzo Reggiardo inspected Thursday, is about 90% complete with a trial operation slated to start in roughly two months.
  • It creates a direct connection between Estación Central of the Metropolitano and Metro Line 1’s Grau station to cut transfer times for riders.
  • City estimates say a trip from Carabayllo to Estación Grau could take about 30 minutes once the link is in use.
  • The project spans 2.8 km with an investment of S/115 million, and it includes new pavement, sidewalks, curbs, trees, and green areas.
  • Structures for the Abancay, Andahuaylas, and Parinacochas stations are finished, and crews are installing floors, roofs, ramps, glass, and signs while adding smart signals, sensor doors, and controlled access for safer, smoother operations during the trial phase.