Overview
- The marcha blanca began January 9 with two lanes open west to east, allowing private cars, public buses and heavy trucks only within daytime hours.
- LED lighting installation remains pending for one to two weeks, after which continuous operation is planned in the Lima‑to‑Chosica direction.
- Traffic from Chosica to Lima awaits relocation of a natural gas interference expected in about 20 days, with full bi‑directional opening projected for February.
- EMAPE reports 95% completion of the third‑level viaduct built in roughly seven months using prefabricated elements, with six total lanes and beams up to 40 meters.
- Municipal estimates forecast travel times dropping from about 150 minutes to roughly 45 minutes for more than 2 million residents, as ATU readies stops and tests express services with Etul4, Vargasant, Los Loritos and Nueva Era.