Overview
- Trial operations run from 5:00 a.m. to 6:00 p.m. with two lanes open in the Lima-to-Chosica direction.
- Private cars, public buses and heavy cargo trucks may use the bypass during the trial hours.
- Construction stands at roughly 95% completion, with final lighting, signage and interference relocations pending before full opening.
- Authorities project travel times on Ramiro Prialé to drop from about 150 minutes to roughly 45 minutes, benefiting more than two million residents in eastern Lima.
- ATU is coordinating express bus services and restoring stops, with operators such as Etul 4 and Los Loritos expressing interest.