Key Bridge Rebuild Shows Major Foundation Progress as State Breaks Project Into Multiple Contracts

Officials say progress so far keeps the replacement on track for late 2030 completion pending contractor proposals.

Overview

  • The Maryland Transportation Authority told reporters Wednesday that 80 of the 90 eight‑foot‑diameter foundation piles have been installed in the Patapsco River to support the new cable‑stayed main span.
  • Engineers said the piles measure roughly 200 to 230 feet long with about 1.5‑inch steel walls, and they are sized larger than the old bridge to carry greater loads.
  • State leaders have moved away from a single Phase 1 contractor after a cost dispute with Kiewit and are splitting work into four contracts to seek new bidders and boost competition.
  • Bidding opened this week for the second contract, which covers demolition and debris removal, and officials say Kiewit is scheduled to finish remaining pile work by early spring 2027.
  • The project remains estimated in the $4.2 billion to $5.3 billion range and officials warn that final schedule certainty depends on incoming contractor proposals and the timing of contract awards.