KDWSP Phase II Pumping Main Repairs Near Completion and Water Board Issues Scam Alert

Phased pipeline charging is scheduled to begin late Monday to protect the 2,375‑mm main and restore water service to affected areas.

Overview

  • The Hyderabad Metropolitan Water Supply and Sewerage Board said work on the 2,375‑mm MS pumping main between Nasarlapally and Godakondla is nearing completion after a planned shutdown for repairs.
  • Crews replaced air valve tees at 45 locations and fixed a scour valve leak at Kurmed village, with final tasks due to finish before pipeline charging begins.
  • HMWS&SB set a phased charging plan to bring the pipeline back online, a process designed to avoid pressure surges that can damage large‑diameter mains.
  • The board warned customers about fraudsters posing as officials and advised against clicking unknown links, installing APKs, granting screen access, or sharing OTPs and payment details.
  • Consumers were told to use only official HMWS&SB channels for bills, to preserve evidence of suspicious contacts, and to report suspect transactions to their bank and cybercrime authorities.