- Segiagua reports the project at 70% progress more than a month after the sinkhole opened in Colonia Renovación.
- Crews have installed a new steel pipeline to replace the damaged concrete line as a reinforcement measure.
- Formwork and concrete pouring are slated midweek, then backfill, reinstatement of water and drainage lines, and asphalt paving through the weekend.
- An initial 15–20 day estimate slipped due to persistent storms and asphalt settlement, according to officials.
- The schedule remains contingent on no further complications, and authorities say safety around nearby homes has been a priority after the widely shared truck incident.