Overview
- Government officials this week forecast a roughly 430 million cubic metre winter gas shortfall, up from about 300 million last year.
- Iran says 26 projectiles hit six processing sites on March 18, 2026, knocking out roughly 28% of production capacity and leaving about 130 million cubic metres per day of damage that may not be fully restored until 2028.
- Authorities have ordered demand cuts including a 20% reduction target for state bodies, office temperature limits, inspections that led to some building disconnections, and priority supply for households over industry.
- Officials warn power plants may burn heavy fuel oil (mazut) when gas is diverted, which will raise air pollution, and that industrial curbs have already forced shutdowns such as a Zagros Petrochemical methanol unit.
- Tehran is exploring short-term options including reported talks to import gas from Russia but experts say sanctions, ageing infrastructure, and a need for foreign investment and technology make a long-term fix difficult.