Invenergy Cancels 2.4-GW Leading Light Wind Off New Jersey

Developers cite unresolved financial, supply chain, regulatory hurdles that leave no viable path under the awarded terms.

Overview

  • Invenergy informed the New Jersey Board of Public Utilities that the Leading Light Wind project is canceled after concluding it cannot proceed under its OREC award.
  • Filings attribute the decision to cost pressures, supply shortages, vendor constraints, shifting requirements, and an inability to secure a turbine supplier.
  • The 2.4 GW project was planned about 40 miles off New Jersey with an initial goal of 2030 operation.
  • Developers previously obtained multiple extensions and a stay after missing filing milestones, then determined they could not meet lease obligations.
  • Invenergy said it regrets the decision and may consider future solicitations, as other developers such as JERA Nex BP also scale back U.S. offshore wind investments.