Overview
- An official source says the Centre is likely to grant a second extension to PM-KUSUM to allow more time to meet the scheme’s targets.
- Component A has reached just 6.5% progress, totaling 650.49 MW installed capacity as of September 9.
- Under Component C for solarising grid-connected pumps, progress stands at 16.5% for the IPS segment and 25.5% for the FLS segment.
- Component B has seen relatively stronger uptake, with over 12.72 lakh off-grid pumps sanctioned and 9.03 lakh installed, while Andaman and Nicobar, Puducherry, and Telangana reported nil installations.
- States reported uneven implementation under Component A, with nil installations in Telangana, Tripura, Odisha, Gujarat, and Assam, and single-digit megawatt additions in Uttar Pradesh, Tamil Nadu, Maharashtra, Goa, and Chhattisgarh.