- Groundbreaking is planned for April 2026 at Eastport Industrial Park on Zoo Parkway, with commissioning targeted for the second half of 2027.
- The factory is estimated at about 500,000 square feet with a roughly $100 million build cost, supported by a reported $7.5 million city construction grant.
- Holon will base its U.S. headquarters in Jacksonville, and InLight Real Estate Partners is the development partner for the site.
- JTA intends to purchase Holon’s 12-passenger Urban shuttles for the NAVI service once production begins, integrating them into Downtown operations.
- Employment and impact figures are projections, with about 150 direct jobs at launch and studies citing more than $200 million during construction and roughly $87 million in annual output beginning in 2028.