- Hashrate stands at 23 exahashes per second after 283% year‑to‑date growth, with HIVE saying it is on track to hit 25 EH/s before the end of November.
- The ramp is driven by full hardware deployment at a 100 MW hydroelectric campus in Paraguay energized by the Itaipú Dam.
- HIVE acquired land in Grand Falls, New Brunswick, for a planned Tier III+ high‑performance computing site that the company says could host about 25,000 GPUs.
- Retrofitting in Boden, Sweden, and a Toronto buildout with a Bell colocation partnership are part of a push that projects roughly 36,000 GPUs by end‑2026, up from about 5,000 today.
- The firm holds approximately 2,201 BTC in its treasury, and its shares declined in pre‑market trading on the reporting day.