Overview
- Chief secretary Sanjay Gupta directed departments to accelerate restoration on about 120 rain-hit roads with a target to reopen most by the end of October.
- The NHAI regional officer assured that the Kiratpur–Manali highway is operating with at least two lanes across all stretches that saw monsoon damage.
- Education minister Rohit Thakur instructed the PWD to use the best available technology and climate-resilient designs, including options like bailey bridges where needed.
- Officials reported that all damaged roads are open to small vehicles, with roughly 14 routes still closed to heavy vehicles slated for priority reopening.
- Recovery steps include issuing all PDNA-related tenders by November 15 and advancing PWD collaboration with IIT Ropar, with a focus on strengthening existing roads and planning safe muck disposal.