Overview
- NHAI may resume collection at the Sanwara plaza on November 12 only if court‑mandated rectification is completed within 10 days.
- The order requires clearing muck and drains and urgent fixes at Datyar, Chakki Moud, the Kandaghat approach and market stretch, and surfacing at Shimla’s Boileauganj U‑turn.
- The court directed the state to provide police assistance to overcome local obstructions and suggested night or early‑morning work to limit disruption.
- NHAI reported awarding a ₹15.20 crore, 12‑month maintenance contract to NH Construction Pvt. Ltd. and acknowledged significant delays.
- Status affidavits note slope protection done at 30 of 42 sites, roughly 2.3 km still restricted to two or three lanes, and ₹4.53 crore in toll revenue lost during the closure.