Particle.news

High-Tech Control Room Near Ram Temple Completed in Ayodhya

Commissioning is expected soon as boundary-wall work wraps up.

Overview

  • The Uttar Pradesh Home Department built a G+1 administrative building with a basement control room on 12,000 sq ft of police land just outside the Ram Janmabhoomi Teerth Kshetra.
  • The facility will be operated by the police to enable close surveillance of the temple vicinity.
  • The control room supports real-time CCTV monitoring, crowd movement tracking, traffic regulation and emergency response coordination.
  • Construction began in December 2023 under Construction and Design Services (C&DS/CNDS), with officials saying roughly 98% of work is done and the site ready for inauguration.
  • Reports differ on the project cost, with figures of ₹11.28 crore and ₹112.87 crore both cited by outlets referencing the same official note.