A peer‑reviewed Harvard inventory released Monday shows concentrated electricity demand and heavy fossil‑fuel sourcing that helped prompt widespread local bans and voluntary industry pledges while leaving on‑site generation unmeasured.

Overview

  • The Harvard‑led study released Monday estimated 403 U.S. hyperscale facilities used about 68–99 terawatt‑hours of electricity in May 2024–April 2025 and were associated with roughly 25.7 million metric tons of CO2.
  • Researchers attributed roughly 54 percent of that power to fossil fuels, mostly natural gas and coal, and found that Virginia, Oregon, Ohio and Iowa together accounted for more than half of the load.
  • Voter anger over local impacts translated into near‑universal ballot defeats for new projects, with about 40 of 41 local measures in the midterms limiting or banning data center expansion and prompting state moratoria and permit pauses.
  • Major cloud companies have offered voluntary fixes such as paying local power costs, funding community programs and rebranding campuses, and OpenAI’s CEO Sam Altman acknowledged on Monday that current community engagement is failing even as firms push to build capacity.
  • The study likely understates today’s totals because it excludes on‑site generation and facilities completed after April 2025, a gap that heightens concerns about grid strain, uncounted emissions and whether voluntary pledges will be enough to protect local power bills and air quality.