Particle.news

Download on the App Store

Harris County Closes and Pauses Dozens of Flood Projects as Costs Outrun 2018 Bond

Officials now estimate about $410 million is required to finish unfunded work, leaving open a possible request to taxpayers.

Overview

  • At Thursday’s Commissioners Court, leaders said 15 never-started projects are closed, 26 active projects are on hold, 75 under construction will proceed to completion, and 54 are already finished.
  • The flood control district director said roughly $410 million is needed to complete the projects that currently lack funding.
  • Officials cited higher construction costs and about 8% inflation as key reasons the bond program’s purchasing power fell short.
  • ABC13 has reported a broader shortfall near $1.3 billion for the 2018 bond program, with 111 of 181 project areas described as in limbo.
  • Residents and advocates voiced frustration over fairness and priorities, including criticism that the adopted framework was not properly followed.