Overview
- Project firm Deges confirmed construction on the replacement Ringbahn bridge will begin on October 20 with completion targeted for summer 2027, with Berlin mayor Kai Wegner expected at the groundbreaking.
- An intensive shutdown at the Funkturm interchange is scheduled from October 30 at 22:00 to November 3 at 05:00 to remove the closed Halenseestraße Ost overbridge, severing key A115–A100 links and closing sections of Messedamm and Halenseestraße Ost.
- Autobahn GmbH found spalling concrete and corrosion on the A100 bridge over Mecklenburgische Straße, closing the outer lane toward Dreieck Funkturm and the Detmolder Straße on‑ramp from October 10 at 10:00, with investigations due to finish by late November and an HGV overtaking ban in place.
- Hamburg’s Köhlbrandbrücke will be fully closed from October 10 at 22:00 to October 13 at 05:00 for urgent maintenance, with police warning of major disruption and signposted detours and further full‑weekend closures planned in 2026.
- Authorities present the Berlin works as part of a wider renewal push, with €150 million in federal funding reported for the Ringbahn bridge rebuild and speed‑focused tenders aimed at limiting traffic impacts.