Gávea Metro Station Begins Permanent Rail Installation

Starting rail work clears a major engineering barrier, signaling the project can meet a mid-2028 opening.

Overview

  • Officials confirmed late Friday that crews have begun installing the first permanent rails in the tunnel linking Gávea and São Conrado, marking the first time the line has received its permanent track since works restarted.
  • The construction restart was enabled by a 2024 TCE-RJ agreement that assigned R$697 million for completion, extended the metro concession to 2048, and led to an official resumption of work in April 2025.
  • The project has overcome unusual technical hurdles from the halt: engineers purposely flooded two roughly 50-meter shafts in 2018 to stabilize soil pressure, then carried out a controlled dewatering process under INEA oversight that concluded in December 2025.
  • Since dewatering, teams removed more than 28,000 tonnes of rock and completed tunnel excavation phases; current work includes porous concrete, drainage, sleepers and a ballast slab with final rail fixation and systems installation to follow.
  • When finished the station will link a 3.2 km stretch between Gávea and São Conrado and is projected to serve about 20,000 daily users, but the project still needs internal fit-out, a substation, signaling and testing before the government’s mid-2028 opening target can be met.