Overview
- Patel ordered completion of farmer compensation for the Mumbai-Ahmedabad high-speed rail corridor by August 2025 to clear land acquisition hurdles.
- The 30 GW hybrid renewable energy park at Khavda, Kutch, has reached 64% completion with 6,862 MW operational and full commissioning aimed for December 2026.
- At Lothal, officials have allocated 400 acres of land and laid water pipelines and electricity lines for the National Maritime Heritage Complex, accompanied by road-widening works.
- Urban renewal projects in Gujarat, including the Sabarmati riverfront redevelopment and Surat’s Dream City infrastructure master plan, advanced following detailed briefings by development corporations.
- Construction of Kaushalya Skill University has been fast-tracked with expedited timelines to bolster Gujarat’s human capital development.