The inspector now reviews objections alongside the developer’s case before a final ruling.

Overview

  • Officials from the Planning Inspectorate, the applicant and local opponents presented evidence at a public hearing at County Hall in Durham.
  • Durham County Council’s December 2024 approval is under reconsideration following complaints about inadequate local consultation.
  • More than 800 objections cite odour, noise, heavy-vehicle traffic and incompatibility with nearby farmland and community amenities.
  • Knotty Hill Golf Centre, located within metres of the site, warned the project could harm the golfing experience and threaten its viability.