Overview
- Kairos Power’s Hermes 2 reactor in Oak Ridge will supply 50 megawatts to the TVA grid under a new PPA, with Google receiving clean energy credits to match usage at data centers in Tennessee and Alabama.
- The agreement is the first time a U.S. utility has committed to buy electricity from a Generation IV advanced nuclear plant, according to the companies.
- Hermes 2 has an NRC construction permit issued in November 2024, while the reactor still requires an operating license before generating power.
- The design is a fluoride salt‑cooled, high‑temperature reactor using molten salt coolant and HALEU‑based TRISO fuel, with workforce training planned through the University of Tennessee.
- The plant is the initial step in Google’s collaboration with Kairos to deploy up to 500 megawatts of advanced nuclear capacity over the next decade, with financial terms of the current deal undisclosed.