- Under the agreement, TVA will purchase 50 MW from Kairos Power’s Hermes 2 demonstration plant in Oak Ridge beginning in 2030, and Google will secure the reactor’s clean-energy attributes for its Tennessee and Alabama data centers.
- Hermes 2 represents the first U.S. utility power purchase agreement for a Generation IV nuclear reactor, leveraging a molten-salt cooling system instead of water.
- Kairos Power has obtained Nuclear Regulatory Commission construction permits for the Oak Ridge site but must still secure an operating license and complete full regulatory clearances to meet the planned startup.
- The Department of Energy has supported Kairos through its Advanced Reactor Demonstration Program, offering technical and regulatory assistance for commercial deployment.
- Local partnerships with the University of Tennessee and other institutions will develop workforce training programs as Oak Ridge reestablishes itself as a nuclear innovation hub.