Overview
- Augas de Galicia’s revised scheme retains prior structural and environmental measures while increasing the budget to €3.5 million
- The draft includes a parallel road and provisional bridge over the Miñor River to maintain traffic flow during viaduct construction
- The municipal council and residents’ association have expressed willingness to collaborate but are seeking detailed negotiations on land use agreements and execution plans
- The project design is slated for completion by December 2025, paving the way for tenders and a planned summer 2026 start
- A previous €2.2 million contract awarded in November 2022 was terminated after two years of delays over land access and traffic routing disputes