Future USS John F. Kennedy Begins First Builder’s Sea Trials

The Navy now targets March 2027 delivery due to pending arresting gear certification alongside weapons elevator completion.

Overview

  • On January 28, 2026, the future USS John F. Kennedy (CVN-79) departed Newport News under its own power to start builder’s sea trials.
  • This first at-sea period tests core ship systems and components in open water before subsequent Navy acceptance trials.
  • Official budget documents list delivery in March 2027 after a slip from July 2025 to accommodate Advanced Arresting Gear certification and continued Advanced Weapons Elevator work.
  • CVN-79 debuts the AN/SPY-6(V)3 radar and carries EMALS, AAG, and Advanced Weapons Elevators, systems whose integration has previously challenged Ford-class schedules.
  • Delays intersect with retirements of older carriers, temporarily lowering the active fleet to 10 carriers, with Kennedy planned for a Kitsap-Bremerton homeport no earlier than 2029.