Franchi Renovation Delay Pushes Curva Fiesole Reopening to 2027

City officials attribute the slip to steel supply setbacks and unforeseen ground conditions at Campo di Marte.

Overview

  • The mayor of Florence unveiled a revised schedule that shifts completion of the first lot, including the Curva Fiesole, to the early months of 2027.
  • The overall renovation timeline for the Artemio Franchi stadium remains set for 2029, according to the municipality.
  • Technical notes cite longer procurement times for steel roof structures and a switch from helical to drilled piles due to unexpected subsoil characteristics.
  • ACF Fiorentina issued an official statement expressing discontent, warning of possible months away from the ground and signaling it may reassess its involvement in the project.
  • Work continues with reinforced concrete supports rising for the new curve, restoration of the Torre di Maratona nearing completion, demolition for new underground spaces underway, and metal stand structures slated to begin installation early next year.