Overview
- Works are confirmed to run from 3 November 2025 to 1 March 2026, with full closures at times because the trunk road through town is too narrow for safe traffic flow during resurfacing.
- All traffic management will be removed from 5 December to 5 January to ease festive travel, with no work during the Royal Welsh Winter Fair period as outlined by the mayor.
- The project is organised in three phases, with the mayor detailing street-by-street sequencing and a mix of night, day and weekend working to manage local impact.
- A public drop‑in will take place at Strand Hall on Wednesday 15 October for residents and businesses to view plans and raise questions.
- Formal notifications and diversion details will be published on Traffic Wales, and the works form part of a programme targeting an extra 100 km of resurfacing after £81m spent since 2021, rising to £118m by the end of the Senedd term.