Fort McCoy Officers Quarters Project Hits 38% Completion as Winter Work Pushes Ahead

The $55.76 million, two-building effort remains on schedule for a Dec. 31, 2027 finish.

Overview

  • A Dec. 19 update from the U.S. Army Corps of Engineers reported progress rising to 38% from 33% on Nov. 21.
  • Current work includes exterior wall framing, MEP rough‑ins, spray foam, masonry, roof panel staging, structural steel erection, winterization, and interior concrete stair placement.
  • Contractor BlindermanPower is executing a 1,260‑day contract that began with a notice to proceed on July 19, 2024.
  • The facilities replace World War II‑era transient officer quarters and are designed to be deactivated in winter to reduce energy and operating costs.
  • Separately, 14 new concrete pads in the Commemorative Area were finished in October and outfitted on Nov. 20, with work unaffected by the October shutdown.