Finland Orders Halt to Preparatory Work at Google Data‑Center Sites Over Possible Illegal Clearing

LVV paused major clearing at Muhos and Kajaani to determine whether an environmental impact assessment was required.

Overview

  • The supervisory authority LVV ordered a stop to preparatory measures that could harm the environment at Muhos and Kajaani, a move announced on Tuesday while it opens a formal probe.
  • LVV is investigating whether Tuike Finland, Google’s local representative, cleared hundreds of hectares without the environmental impact assessment required by law when permanent clearing exceeds the 200‑hectare threshold.
  • The authority set firm deadlines: Tuike must notify LVV by October 14 whether it will comply and must end specified clearing and earthworks by October 23 or face coercive measures including fines.
  • Google/Tuike has acknowledged shortcomings, said it will review and follow LVV’s recommendations, and has indicated willingness to cooperate with remediation steps reported by local media.
  • The rulings put a brake on a planned at‑least €13 billion expansion that has divided small communities that welcome jobs but worry over energy, water use and loss of protected nature as citizens pressed government oversight.