Overview
- The final rehabilitation of the Willy-Brandt-Straße segment between Domstraße and the Deichtortunnel runs from August 4 until spring 2026.
- During construction westbound traffic will generally have two lanes open while eastbound maintains at least one, with temporary full closures at Brandstwiete, Meßberg and Deichtorplatz ramps.
- Dovenfleet will operate as an eastbound one-way street and the Deichtortunnel will close briefly during the autumn school break.
- Sidewalks and bicycle paths are set for modernization while Hamburger Energienetze installs a new high-voltage line between Umspannwerk Mitte and Tiefstack.
- Work crews will operate six days per week plus select weekends and holidays using multiple teams to accelerate progress and limit peak-hour disruptions.