Overview
- At their first open meeting, Chair Laura Swett and Commissioner David LaCerte said quickly and durably connecting AI data centers is a top priority to support the economy and national security.
- DOE has asked FERC to finalize new large‑load interconnection rules by April 30, and Swett did not say the commission will meet that date as it continues to gather stakeholder input.
- LaCerte stressed that FERC must shield residential customers from undue costs tied to data center hookups and related grid upgrades.
- FERC opened notices of inquiry on creating “blanket” authorizations for certain activities at LNG and hydroelectric facilities, with comments due 60 days after publication in the Federal Register.
- FERC staff projected a 26% rise in average winter natural gas prices, citing higher LNG export demand, as state regulators warn about cost shifts and a bipartisan Senate letter backs a strong federal role with protections for existing customers and respect for state authority.