- FEMA announced on Monday that it approved more than $21 million for Blue Earth County Public Works to remove Rapidan Dam and pay related cleanup and recovery costs.
- The funding, delivered through FEMA’s Public Assistance program, will cover demolition of the partially failed structure, removal of debris, and riverbank restoration.
- Plans funded by the award call for restoring both banks of the Blue Earth River at the dam site and constructing a parking area at the bottom of the river to support future public access.
- The dam partially failed and was overtopped during June 2024 floods, which carved a new channel around the west abutment and caused loss of nearby land and property.
- Built in 1910 and long out of service after 2019 flood damage, the dam had been rated in poor condition with a 'significant' hazard classification in April 2023, and the federal award fills a funding shortfall after a prior state pledge did not appear in the budget.