Overview
- The project company reports the ship Ivy still needs extensive testing and regulatory approvals before installation can begin.
- Femern A/S describes meeting the original timetable as challenging and says it is unclear how much lost time can be recovered.
- Danish-side rail works remain on schedule, according to the company.
- The 18-kilometre road and rail link is designed to sharply shorten travel between the Hamburg and Copenhagen regions.
- German feeder projects face their own delays, with the Fehmarnsund Tunnel currently forecast to complete around late 2031, raising the likelihood that full rail service would start after 2029.