Overview
- Vialidad Nacional must begin immediate safety works on the 120 km stretch, addressing potholes, ruts, deformations, shoulder drop-offs, and missing horizontal and vertical signage.
- The ruling sets a 90-day deadline for a full technical survey with a work schedule, plus reports on rockfall risk and the need for freight weight controls.
- Within 120 days, the agency must file a comprehensive maintenance plan to preserve the corridor after the urgent fixes.
- Judge Gustavo Villanueva's Bariloche federal court barred administrative reprogramming or delays and charged the works to the 2024 budget.
- The case stems from a province-led amparo backed by Governor Alberto Weretilneck, with a related Route 151 order still tied up on appeal by the national government.