Overview
- DEK said it limited electricity to facilities used by PSO Kazan at the Angara launch complex construction zone.
- The utility reports arrears exceeding 51 million rubles for consumed power by the general contractor.
- The spaceport’s director says Vostochny is operating normally, with strategic areas unaffected by the restrictions.
- PSO Kazan previously promised payments in March and again by October 20 but did not pay, and its sites consume about 4 million rubles in power monthly.