Overview
- The start of Phase 2 follows the arrival of the Nguya FLNG and the introduction of gas into new offshore infrastructure.
- Saipem confirmed first gas on the converted Scarabeo 5 floating production unit, highlighting the accelerated timeline.
- Phase 2 comprises three production platforms, the Scarabeo 5 gas treatment and compression unit, and the Nguya FLNG for liquefaction and export.
- The setup develops Marine XII resources at the Nené and Litchendjili fields and supports supplies to both Nguya and the Tango FLNG operating since late 2023.
- Eni cites delivery 35 months after FLNG construction began, a capacity of 3 mtpa or 4.5 bcm per year, local execution, and emissions‑reduction technologies, with the first cargo targeted in early 2026.