EnBW Presents 800 MWh Grid-Scale Battery Plan at Philippsburg

The facility will tap existing grid links to cover costs through market revenues, now awaiting a final investment decision.

Overview

  • The plan was formally presented to the local council, marking a key step toward securing the necessary permits for the 800 MWh installation.
  • The proposed storage capacity matches the daily electricity needs of about 100,000 households, making it one of Germany’s largest battery systems.
  • Project planners will leverage an on-site TransnetBW high-voltage DC converter to integrate surplus wind and solar power into the grid.
  • EnBW intends to finance the project entirely through energy market revenues and grid-service offerings without relying on state subsidies.
  • The battery could be commissioned by the end of 2027 if EnBW grants final investment approval and obtains a building permit.