Overview
- AMEQ and the Municipality of Querétaro will present the alternate‑route and service‑adjustment plan on January 20.
- The state Mobility Agency is preparing contingencies for 22 Qrobús routes that use Prolongación Corregidora Norte, aiming to limit disruption for roughly 80,000 users.
- Only one lane will remain open in each direction on Prolongación Corregidora Norte during the project, municipal officials said.
- Authorities indicate demolition and reconstruction will span about eight months, with schedules aligning with related work at the Bernardo Quintana rail bridge through August.
- The state has begun outreach in 12 nearby neighborhoods as residents and merchants report uncertainty over forthcoming traffic changes.