Ejipura Flyover Crosses 60% Milestone With Bengaluru Eyeing Year-End Target

Major pillar installations paired with ecological transplants set the stage for the corridor’s December 2025 opening.

The 2.5-km-long Ejipura flyover, whose construction began in 2017, has faced years of setbacks and delays.
Image
Bengaluru: Officials Give Big Update on Ejipura Flyover; Here’s How It Will Ease Koramangala Traffic

Overview

  • Construction has reached 60% with 70 of 84 pillars in place and 325 of 762 segments installed along the 2.5-km stretch
  • Down and up ramps at Madiwala-Ejipura and a Sarjapur loop are under development to integrate the elevated corridor into the wider road network
  • Hyderabad-based BSCPCL Pvt Ltd took over in November 2023 after Simplex Infrastructure’s contract was terminated and holds a 15-month deadline for completion
  • BBMP’s revised project cost is Rs 176.1 crore, Rs 48 crore above the original estimate, with Rs 52.1 crore disbursed to the contractor to date
  • Upon opening, the flyover linking Ejipura Main Road to Kendriya Sadan Junction is projected to significantly ease traffic on Koramangala’s 100-Feet Road