Overview
- Metrolinx said the September goal is off and it is now aiming for an October opening window.
- The required 30-day revenue service demonstration has not begun, with officials hoping to start it within weeks before any passenger launch.
- Testing has identified intermittent HVAC and communications issues and faster-than-expected brake wear that crews are diagnosing and addressing.
- The TTC, which assumed operational control in June, says it will not open the line until safety and customer experience standards are met, as Ontario’s transportation minister expressed full confidence in Metrolinx.
- Metrolinx plans a gradual ramp-up of service at opening, says it is applying lessons from Ottawa’s LRT, and indicated the Finch West LRT is tracking a similar timeline.