Econergy Secures €229m Financing for Părău 2 Solar‑Plus‑Storage in Romania

The package pairs a 15-year, 125 MW capacity contract for difference with an InvestEU-backed loan to strengthen bankability and speed project delivery.

Overview

  • On Monday Econergy signed financing agreements with a six-lender consortium led by the EBRD and BSTDB for an aggregate package of about €229 million.
  • Părău 2 combines a 342 MWp solar PV plant with a 150 MW battery energy storage system to store on-site generation and deliver power when the grid needs it.
  • The project holds a 125 MW CfD for 15 years, reported at €49.4/MWh by some outlets and US$57.18/MWh by others, a difference that reflects currency or reporting variances.
  • Roughly €114.4 million of the main facility is covered by an EU InvestEU guarantee to lower perceived revenue risk and financial close is expected within about three months subject to customary conditions.
  • The deal, which follows an earlier-reported EPC agreement with Shanghai Electric and phase-one commissioning in 2024, underlines Romania's rapid growth in large-scale battery storage and supports Econergy's wider pipeline of hybrid projects across Europe.